Files
acdl/.ciagent/VERIFY.md
T
Jon Chery 81c6e3995e docs(P11): plan + verify + verify_phase11.sh (v1.2.1)
---ci---
project: acdl
phase: 11
milestone: v1.2
status: verify
verdict: VERIFIED
requirements:
  covered: [REQ-29]
---/ci---

Phase 11 plan-as-execute + verify. scripts/verify_phase11.sh green (24
assertions). Plan + VERIFY committed. Ready to ship v1.2.1.
2026-07-21 20:57:45 +00:00

75 lines
3.9 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
# Phase 11 — v1.2-research-and-readme (v1.2) VERIFY
**Verdict: Phase 11: VERIFIED**
**Tag: v1.2.1**
**Date: 2026-07-21**
---
## Scope
Phase 11 is a docs-only phase: re-evaluate go-gitea/gitea#36988, audit the
v1.1 spike for NFR gaps + simplification opportunities, and rewrite
`README.md` to reflect v1.1 complete + the actual platform flow + the v1.2
objective. Requirement covered: **REQ-29**.
## Verification layers
### 1. Structural
- `README.md` exists (52 → 144 lines, +92).
- `.ciagent/RESEARCH.md` has a `## v1.2 Research Addendum (Phase 11, 2026-07-21)` section (Targets 913 + decisions table).
- `scripts/verify_phase11.sh` exists (+x, 39 lines).
- `.ciagent/PLAN.md` updated to Phase 11.
- No new executable code; no schema changes; no AWS changes.
- **PASS.**
### 2. Behavioral (`scripts/verify_phase11.sh`)
```
=== Phase 11 verification ===
README.md: OK (v1.2 framing, platform flow, how-to-run, credentials)
RESEARCH.md: OK (v1.2 addendum, Targets 9-13, D-047/D-048/D-049)
.ciagent/ files: OK (v1.2 milestone consistent across all 5 files)
#36988 re-check: OK (date + D-039 extension recorded)
=== Phase 11: VERIFIED ===
```
All 24 assertions pass:
- README.md: `v1.2 (active)` present; `v1.1 (active)` absent; v1.1 marked complete; `v1.3.0` ship tag referenced; D-047 referenced; "How the platform works" section present; spike flow (terraform plan, confidence signal, DynamoDB outbox) documented; `run_spike_e2e.sh` in how-to-run.
- RESEARCH.md: v1.2 addendum section; Targets 913; D-047/D-048/D-049; "still open" for #36988.
- `.ciagent/` consistency: config.json milestone v1.2; PROJECT.md v1.2 objective; REQUIREMENTS.md REQ-29; ROADMAP.md Phase 11; ARCHITECTURE.md v1.2 scope.
- #36988 re-check: 2026-05-27 last-updated date recorded; D-039 waiver extension recorded.
- **PASS.**
### 3. Security
- No credentials introduced or modified. The README documents the D-039/D-047 waiver and links to #36988 but does not embed any AWS key material.
- RESEARCH.md's P1-1 redaction target (two AWS access key IDs in `.ciagent/VERIFY.md` Phase 09 narrative) is *documented* as a Phase 12 action — not yet redacted (Phase 12 scope). No new key IDs introduced in this phase.
- **PASS.**
### 4. Quality
- README.md is accurate against the v1.1 spike codebase (the flow diagram matches `scripts/run_spike_e2e.sh` step-by-step; the repo layout table matches `ls`).
- RESEARCH.md's NFR audit findings are grounded in actual file reads (`spike_runner_policy.json`, `create_state_backend.py`, `create_iam_user.py`, `run_spike_*.sh`, `rotate_spike_key.sh`).
- The #36988 re-check facts (state=open, merged=false, updated_at=2026-05-27) were fetched live from `api.github.com/repos/go-gitea/gitea/pulls/36988` during the research.
- D-047/D-048/D-049 are consistent with the PROJECT.md decisions table and the ROADMAP.md phase descriptions.
- **PASS.**
## P0 / P1
- **P0: none.**
- **P1: none new.** P1-1 (carried forward from v1.1 audit) is explicitly scoped for Phase 12 — the redaction target is identified in RESEARCH.md TARGET 10 but the redaction itself is Phase 12's REQ-30 deliverable.
## Requirements covered
- **REQ-29:** `README.md` is fully rewritten to reflect the v1.1-complete platform: the actual spike flow (contract → IR → `terraform plan` → Checkov → confidence signal → outbox), how to run it (`scripts/run_spike_e2e.sh`; `run_platform.sh` noted as the v1.2 consolidation), the real repo layout, the v1.2 objective, the environments table, and the credentials/D-047 waiver. No stale "v1.1 (active)" framing. **VERIFIED.**
## Conclusion
Phase 11 is VERIFIED. The v1.2 milestone is open with a clear research
baseline: #36988 is still blocked (D-047 extends the waiver), the spike's
NFR gaps are catalogued (Phase 12 scope), the simplification plan is
D-048 (script consolidation), the ECS L1 catalog is scoped (D-049, Phase
13), and the README accurately documents the platform as it exists today.