Jon Chery a288eb93ea docs(P00): create v0.8 phase plans — 4 exec phases + final review
PLAN_v0.8.md (33KB): 4 execution phases, 37 tasks (36 must-haves),
3-wave ordering per phase, persona-assigned (lead/backend/data),
REQ-057..060 mapped.

P01 coverage round 2 (12 tasks): proxmox sessionRunner seam + 9 pkg
tests, tiered floor ≥70%/≥50% per D-047.
P02 SSH trust (11 tasks): --host-key-fingerprint pre-pin + key-reset +
TOFU capture bugfix + HostKeyFingerprint population.
P03 verify-reqs gate (5 tasks): cmd/verify-reqs Go program + make
target + .coreci.yml hook.
P04 final review + ship + audit (9 tasks).

Zero new direct deps. ROADMAP reconciled to 4-phase structure (P04 =
final review, no separate P05).

---ci---
project: orca
phase: 0
milestone: v0.8
status: plan
---/ci---
2026-08-04 00:49:07 +00:00
..
2026-08-03 19:39:14 +00:00
2026-08-03 18:01:16 +00:00
2026-08-03 19:40:21 +00:00
2026-06-03 21:09:15 +00:00
2026-08-03 18:00:26 +00:00
2026-08-03 19:39:14 +00:00