a288eb93ea
PLAN_v0.8.md (33KB): 4 execution phases, 37 tasks (36 must-haves), 3-wave ordering per phase, persona-assigned (lead/backend/data), REQ-057..060 mapped. P01 coverage round 2 (12 tasks): proxmox sessionRunner seam + 9 pkg tests, tiered floor ≥70%/≥50% per D-047. P02 SSH trust (11 tasks): --host-key-fingerprint pre-pin + key-reset + TOFU capture bugfix + HostKeyFingerprint population. P03 verify-reqs gate (5 tasks): cmd/verify-reqs Go program + make target + .coreci.yml hook. P04 final review + ship + audit (9 tasks). Zero new direct deps. ROADMAP reconciled to 4-phase structure (P04 = final review, no separate P05). ---ci--- project: orca phase: 0 milestone: v0.8 status: plan ---/ci---