docs(milestone): complete scheduling-streaming (v0.3)
---ci--- project: orca phase: 3 milestone: v0.3 status: complete requirements: covered: [REQ-022, REQ-030, REQ-032] partial: [] ---/ci--- v0.3 milestone merged to main. Includes all v0.2 work (P08-P10) that was previously on the milestone branch but not yet merged to main, plus the v0.3 completion work (iter.Seq streaming + doctor network/db). v0.2 phases included: P08 (mTLS), P09 (scheduling), P10 (security scan). v0.3 phases: P0 (pre-execution), P1 (iter.Seq streaming), P2 (doctor), P3 (final review+ship). Total: 40 requirements, all complete. No new go.mod dependencies. Full test suite passes under -race. gofmt + go vet clean.