b927f9026a
---ci--- project: acdl phase: 6 milestone: v1.1 status: plan plan: waves: 3 tasks: 6 requirements: [] # repo hygiene; no new REQ ---/ci--- Phase 06 plan authored by ci-planner. 3 waves (strictly ordered): - Wave 1 (lead-developer): T-6.1 git mv demo dirs, T-6.2 scaffold new dirs, T-6.3 write scripts/verify_phase06.sh at top-level, T-6.4 rewrite README + .gitignore - Wave 2 (frontend-engineer): T-6.5 confirm demo/evidence-ui/ moved cleanly (confirm-only) - Wave 3 (lead-developer): T-6.6 run verify_phase06.sh + typecheck gate Key design: v1.1 verify scripts live at a new top-level scripts/ (not demo/scripts/ which holds the archived v1.0 verify scripts). All git mv commands enumerated verbatim in T-6.1, cross-checked against RESEARCH.md TARGET 10.